=====[Nordburg]===== ATLAS RRB, 2004.04.27 3. Status of ATLAS Resources (M. Nordberg) 3.1 Introduction to Funding Agency Tables  ・既に振り込んだ入金、あるいは予定されている入金を理解してもらうのが主な目的  ・M&O、C&I と CC 表はプロジェクトに支払われた総額  ・Cost to Completion (CtC)= Commissioning & Integration (C&I)                + Construction Completion (CC)    - Category A = Common items    - Category B = System-specific items  - 言葉の意味    - Baseline and CC-A     "Contributions by Funding Agencies"= income received from FAs     "New commitments needed" by FAs = new commitments requested from the FAs,                      also beyond the budget year    - M&O, CtC (=C&I+CC)     "Contributions by Funding Agencies"= income received from FAs     "Other income"= contribution advancements for the future; deferral funds;             contributions, transfers from baseline     "Total (actual) payments"= payments made by the Project     "Balance"= total contributions + other income - total payments 3.2 2003年の決算  ・2003年 Baseline Closing Report (MCHF), (Common Projects include CC-A) ============================================================================ Inner LAr Tile Muon TDAQ/ Common Total Det. Cal. Cal. Cham. DCS Prjcts ============================================================================ commitments 7.9 5.5 - 6.6 4.0 16.7 40.7 ---------------------------------------------------------------------------- payments 13.8 5.7 0.1 7.9 3.5 25.3 56.3 ============================================================================  ・2003年 C&I (A + B) (kCHF) ============================================================================ CatA ID LAr TileC Muon CatB A+B ============================================================================ total contributions 1986 825 387 366 399 1977 3963 other income 0 - 135 - - 135 135 total payments 1425 543 697 331 274 1845 3270 ---------------------------------------------------------------------------- balance 828 ============================================================================  ・2003年 CC-B (kCHF) ============================================================================ ID LAr TileC Muon CatB ============================================================================ total contributions 1251 804 613 300 2968 other income - - - - 0 total payments 419 342 97 149 1007 ---------------------------------------------------------------------------- balance 1961 ============================================================================ 3.3 2004年の執行計画 ・2004年 Baseline (MCHF), (Common Projects include CC-A) ============================================================================ Inner LAr Tile Muon TDAQ/ Common Total Det. Cal. Cal. Cham. DCS Prjcts ============================================================================ commitments 9.8 6.1 - 4.8 7.2 22.5 50.4 ---------------------------------------------------------------------------- payments 17.7 7.9 - 6.0 6.7 53.6 91.9 ============================================================================  ・2004年 C&I (A + B) Income & Payments (kCHF) ============================================================================ CatA ID LAr TileC Muon CatB A+B ============================================================================ total contributions 3211 826 330 661 620 2437 5648 other income 1888 0 0 0 0 0 1888 total payments 3900 1316 695 775 850 3636 7536 ---------------------------------------------------------------------------- balance 0 ============================================================================  ・2004年 CC-B Income & Payments (kCHF) ============================================================================ ID LAr TileC Muon CatB ============================================================================ total contributions 1246 568 788 910 3512 other income 535 360 36 450 1381 total payments 1781 928 824 1360 4893 ---------------------------------------------------------------------------- balance 0 ============================================================================ 3.4 2005年の執行計画  - これらはプロジェクトを計画通りに進めるために絶対に必要とする額!!   これ以上の赤字は許容できない  ・2005年 Baseline (MCHF), (Common Projects include CC-A) ============================================================================ Inner LAr Tile Muon TDAQ/ Common Total Det. Cal. Cal. Cham. DCS Prjcts ============================================================================ total contributions 6.9 3.1 - 0.3 9.7 18.2 38.2 ---------------------------------------------------------------------------- total payments 6.9 3.1 - 0.3 9.7 22.1 42.1 ---------------------------------------------------------------------------- balance -3.9 -3.9 ============================================================================  ・2005年 C&I (A + B) Income & Payments (kCHF) ============================================================================ CatA ID LAr TileC Muon CatB A+B ============================================================================ total contributions 2228 538 291 408 281 1618 3846 other income 0 0 0 0 0 0 0 total payments 3520 1006 667 714 450 2837 6357 ---------------------------------------------------------------------------- balance -2511 ============================================================================  ・2005年 CC-B Income & Payments (kCHF) ============================================================================ ID LAr TileC Muon CatB ============================================================================ total contributions 336 277 79 441 1133 other income 0 0 0 0 0 total payments 405 714 100 700 1919 ---------------------------------------------------------------------------- balance -786 ============================================================================ 3.5 Global ATLAS Budget Balance (MCHF) -------------------------------- 年 単年残額 積算残額 -------------------------------- 2003 7 22 2004 -15 7 2005 -17 -10 2006 4 -6 2007 6 0 -------------------------------- - 2003年10月の RRB では 2004年に資金不足が起こると予想された - CERN が(CERN 分の)全 CtC (13.6 MCHF) を支払ってくれたおかげで 2004年の   危機は避けることが出来る  - しかし資金不足の時期が 2005-2007年にシフトしただけで根本的な問題が解決   した訳ではない  - CERN としてはやるだけのことはやった。ほかの Funding Agencies も協力して欲しい - 資金不足の問題を解決するあるいは影響を最小限にするための提案    * FAs は資金貢献を前倒しにして欲しい    * FAs は遅延資金を 2004-2005年に使えるようにして欲しい    * FAs は残りの CtC を出して欲しい    * RRB Chairman は問題を緩和するあらゆる手立てを追及して欲しい 3.6 M&O Income & Payments  ・2003年 M&O, final April 2004 (kCHF) ============================================================================ CatA ID LAr TileC Muon CatB A+B ============================================================================ total contributions 1846 330 77 48 198 653 2499 total payments 1575 527 162 111 247 1047 2622 ---------------------------------------------------------------------------- balance -123 ============================================================================  ・2003年 M&O (Cat. A), Contribution Status (kCHF) ==================================================================== 2002年から 2003年 (A) 2003年 (A) 残額      の繰越額 実貢献額 義務額 -------------------------------------------------------------------- ATLAS 全体 -50 1690 1575 57 ====================================================================  ・2003年 M&O (Cat. B), Contribution Status (kCHF) ==================================================================== 2002年から 2003年 (B) 2003年 (B) 残額      の繰越額 実貢献額 義務額 -------------------------------------------------------------------- ATLAS 全体 309 805 1047 66 ==================================================================== ======= 以上